INTRODUCTION TO QuikBeamAASHTO
A full preliminary analysis of prestressed concrete beams is highly desirable but
seldom performed in practice due to the time consuming requirements in determining
the reinforcement and initial concrete strengths. Design engineers usually face
the situation where several initial estimates of the beam size, amount of reinforcement,
concrete release strength and material quantities are needed before final framing
and layout decisions are made. In the final design stage they will proceed to run
detailed calculations and check conformance to the design requirements. Commonly
used bridge beam types are shown in Figure 1.

Figure 1
Back to top
These tedious design steps usually take a substantial amount of time. Even with
the use of current software available to the designer, the program input and iterations
are still time consuming. Furthermore, a previous design of a 98-feet-span structure,
for example, cannot simply be extrapolated to a subsequent 118-feet-span structure
because of other variables such as girder spacing, concrete strength and beam size
which are associated with a specific project.
In the Type, Size and Locations (T S & L) phase of a bridge selection process,
designers are often faced with the following questions for a bridge with a given
width:
(1) Given an alternative solution with a span, L1, a number of beams, Nb
(or a girder spacing S1), is the solution feasible? The answer is yes, if:
(a) the sections require a number of 1/2 inch strands, N, that is less than
the maximum number physically allowed by the form design, and
(b) if the required release strength for concrete does not exceed a maximum
regional, structural, or producer limit, f'ci.
(2) If one pier is eliminated a new alternate design is possible with a deeper
section and a longer span, L2. Is a new spacing S2<S1 required? Is the solution
in (2) more economical than (1)?
(3) If one girder line is eliminated, would the new solution with a spacing
S3> S1 be feasible and more economical?
A fast prediction of N and f'ci is essential at the conceptual T S & L or
estimating stages since producers have limitations on concrete strengths and the
amount of reinforcement they can place in a beam. In order to answer these questions
in a systematic way, a relationship between N (or f'ci), the girder spacing,
S, and the span, L, was first developed in the early 1990s.
Back to top

Figure 2
In this study, it was assumed that L and S are the dominant variables. Based on
more than 1,100 exact solutions, it was found that the following equations are excellent
predictor formulas (also see Fig. 2 above) where N is the number of standard 1/2
inch diameter, low-relaxation strand, and f'ci is the required concrete release
strength:
N = A(L)x (S)y [1]
f'ci = B(L)u (S)v [2]
QuikBeamAASHTO, a macro driven spreadsheet using sections available in the Central
Atlantic states, was also developed using these equations. For 95% of the cases
the average relative prediction error using Equations [1] and [2] was found to be
4% only, with a range of 0 to 8%. It requires inputting a limited number of data
such as bridge type (I-beam, spread box or adjacent box), bridge width, and simple
span length. Additional variables, such as slab overhang, the minimum number of
girders, smallest desirable beam depth and maximum permissible release strength
are optional. The program then generates up to 9 solutions with prestressing and
strength requirements in addition to summarizing the material quantities (concrete
volume and number of strands).
Back to Top
Preliminary Design Aids : Introduction to QuikBeamAASHTO
